Fourteen new wind farms in Serbia by 2028 – AERS approves EMS' development and investment plans
In the Development Plan for 2019-2028, the list of production capacities expected to be connected to the grid includes 14 new wind farms, one new thermal power plant, a new generator at the Kostolac B thermal power plant (TPP), a generator with an increased installed capacity at TPP Nikola Tesla A, two new thermal power plants (TPP Pančevo and TPP Vinča), a new generator at hydropower plant (HPP) Potpeć, as well as four other generators with an increased installed power at other HPPs, Vladimir Spasić writes for Balkan Green Energy News.
There are also five projects for the connection of facilities installed by the transmission system users, primarily intended to power new mines, the EMS said on its website.
The Investment Plan for the three-year period envisages investments that are important from a national, regional and European perspective, and whose implementation will have a significant impact on increasing the transmission capacity of the regional network as well as on the development of the electricity market in Europe.
– The transmission network’s development planning is becoming an increasingly complex process because there is a growing number of requests for connecting renewable energy sources, while the EMS must also provide the infrastructural conditions for industrial development and fulfill its major task to ensure reliable and secure power supply and a sustainable development of the Serbian transmission system, having in mind the goals of the ENTSO-E Ten Year Network Development Plan (TYNDP) – said Nadica Stojanović, Executive Director of EMS Investment and Strategy.
The Development Plan for 2019-2028 also includes the completion of the first phase of the Trans-Balkan corridor. It includes the completion of the remaining three sections: Section 2 (400 kV power line from substation Kragujevac 2 to substation Kraljevo 3), Section 3 (2×400 kV power line from substation Obrenovac to substation Bajina Bašta), and Section 4 (2×400 kV power line between Serbia, BiH and Montenegro). Section 1 (2×400 kV power line between Serbia and Romania) was commissioned in December 2017.
Most Important News
06.04.2024. | Agriculture
Preconditions for Placement of Fresh Blueberries and Dried Plums in Chinese Market Secured
16.04.2024. | News
Jovan Ciric, Leasing Director Retail MPC Properties – MPC Echo symbolizes our desire for good ideas and innovative endeavors to spread freely and bring about positive changes
16.04.2024. | News
10.04.2024. | Finance, IT, Telecommunications, Tourism, Sports, Culture
Creative Industry – What This Serbian Economy Sector Worth EUR 2 Billion Encompasses
10.04.2024. | Finance, IT, Telecommunications, Tourism, Sports, Culture
27.04.2024. | Construction, Tourism, Sports, Culture
Regional football centers to be built in Novi Sad and Nis
27.04.2024. | Construction, Tourism, Sports, Culture
16.04.2024. | News
Economy Fair in Mostar opens – 26 companies from Serbia exhibiting
16.04.2024. | News
26.04.2024. | Industry, Construction
Plans for continuation of construction of Belgrade sewer system announced – Section beneath river Sava to be 414 meters long, reconstruction of Karaburma tunnel
26.04.2024. | Industry, Construction