Thermoblock B3 online no sooner than spring? - Looking for a new FIDIC engineer
- For objective reasons, there was a delay in the Project (new thermal block B3 in Kostolac), which, due to the exhaustion of the contracted scope of service with the current FIDIC engineer, who will perform this role in the 3rd quarter of 2024, will lead to the need to contract a new FIDIC service engineers - it was stated in the technical specification of the work estimated at almost 135 million dinars (about EUR 1.2 million).
Therefore, as stated, the expected start of this service is tentatively the last quarter of 2024.
As stated, the delay in the implementation of the works was due to the epidemic of the COVID-19 virus, as well as many other influences, partly as a result of "force majeure" and a number of other reasons. Accordingly, t is not currently possible to attach the existing term-plan realization of the Project, but it is possible to predict that the tentative completion of the project implementation activities based on the last submitted work plan by the contractor (the Chinese company CMEC) should not be longer than 6 months from the day of the start of the services defined in this tender documentation - the document states.
FIDIC engineer services under this contract is tentatively planned until the end of 2025, and the tender is open until September 6.
- Will the New Thermal Block B3 at Kostolac Finally Turn the Light On? – EPS Requesting Permit for Commissioning of a Facility with a Power of 350 MW
- What is happening with the new thermal power plant in Kostolac? – EPS commissions supervision over construction of thermal block B3, checking dynamics and quality of works
- Djedovic: Functional tests of block B3 of TPP Kostolac to begin before August
We remind our readers that the Minister of Mining and Energy, Dubravka Djedovic Handanovic, said last month that functional tests are expected to begin before August around block B3 of the "Kostolac" thermal power plant, in order to carry out warranty tests.
It was said that the new 350 MW thermoblock, the first to be commissioned in Serbia since the early 1990s, will be online before the start of the heating season, i.e. in the fall.
The contract on the construction of block B3 was signed by the Government of Serbia and EPS with the Chinese company CMEC back in 2013. The works began five years later, and since then the deadline for their completion has been postponed several times.
B. P.
Naš izbor
Most Important News
07.05.2024. | IT, Telecommunications
Biggest Angular conference in the region – NG Belgrade Conf 2024
06.05.2024. | Healthcare
Medical doctors and engineers from Nis design instrument which accelerates and improves efficiency of operating procedures – Negotiating with foreign companies about production
06.05.2024. | Healthcare
06.05.2024. | Construction, Tourism, Sports, Culture, Healthcare
Sijarinska Banja should soon get a new look – Project documentation for reconstruction of rehabilitation center complex being prepared
06.05.2024. | Construction, Tourism, Sports, Culture, Healthcare
12.09.2024. | News
RIVA Shopping Center opens in Velika Plana on 11,280 m2
12.09.2024. | News
07.05.2024. | Industry, Construction
New Palfinger factory in Nis to start working in June
07.05.2024. | Industry, Construction
12.09.2024. | Energy
First local factory which produces pellets from solar energy
12.09.2024. | Energy