Part of Project for Traffic Route “Vojvodina Smile” Finished – Value of Works Estimated at EUR 1.5 Billion

The traffic infrastructure in Vojvodina was slow to follow the needs and the development of this region, and the new traffic route will fix that, especially in a part of Banat. The new section from the Backi Breg border crossing with Hungary, through Sombor, Kula, Vrbas, Becej, Novi Becej and Kikinda will end with two branches with the neighboring Romania, near Nakovo and Srpska Crnja.
– The construction project and the permit for the first section are finished. The road itself is split into eight sections, which amounts to a length of around 20 km from Backi Breg to Sombor – Nemanja Erceg, the provincial secretariat for urban planning and environmental protection, stated for RTV.
The new corridor, 175 km long, will have four lanes 3.5 meters wide each, and the fact that, on the first section alone, nine overpasses and seven bridges will be built over several water flows and farm roads, illustrates how demanding the works are. In addition to improved connectivity and increased traffic safety, this section, in addition to its national importance, also has international importance, because it will connect three pan-European corridors, says professor Vuk Bogdanovic of the Faculty of Technical Sciences, Department of Traffic Engineering, in Novi Sad.
– The corridor which starts in Budapest and then goes down through Svilaj, Sarajevo, Mostar, to the Port of Ploce and the Budapest-Novi Sad-Belgrade branch of Corridor 10 and Corridor 4, which goes from Budapest through Timisoara, Sofia, to Istanbul – confirmed Bogdanovic.
The value of the project is EUR 1.5 billion, and according to the announcements, the corridor named “Vojvodina Smile” should be completed in five years.
Take a look at the info-map Construction of Highways and Fast Roads in Serbia and the Region.


Naš izbor
Most Important News
13.11.2023. | Transport
State Becomes Owner of 100% of Shares of Air Serbia

13.11.2023. | Finance, IT, Telecommunications
Customs Administration Starts Applying eCustoms System

13.11.2023. | Finance, IT, Telecommunications
13.11.2023. | Industry, Construction, Transport
Machines for Production of Batteries and Fuel Cells to Be Assembled in Stara Pazova – Muehlbauer Automation to Build Technology Park Worth EUR 29.5 Million

13.11.2023. | Industry, Construction, Transport
06.12.2023. | Energy, Construction
Hungary-Serbia Oil Pipeline Pronounced Project of Importance for Our Country

06.12.2023. | Energy, Construction
12.11.2023. | Construction, Transport
Krusevac to Be Connected to Highway in Early December?

12.11.2023. | Construction, Transport
07.12.2023. | Construction, Transport
Morava Corridor Section from Makresane to Kosevi Opens to Traffic

07.12.2023. | Construction, Transport