Details of Relevant Legislation
(*68) This evidence for issuing of the location permit is exactly the same as for issuing the Construction Permit. As evidence of the ownership right, or of lease of the construction land for construction or for carrying out of the work on the construction land or on the facility, which is owned by a number of persons – a certified consent of such persons shall also be submitted.
(*69) When construction of line infrastructure facilities is in question, the decision of the competent authority establishing the public interest for expropriation, in compliance with a special law, or the servitude and right-of-way agreement with the owner of the servient estate, shall serve as the evidence of the ownership right for issuing the location permit.
(*70) In practice, for obtaining the location permit, the general design (conceptual design) is prepared and submitted, which contains: technical description of the location, architecture, the structure and foundation of the structure, the method of heating and cooling the structure, description of the technical solution for securing excavation of the foundation pit, the terrain and the adjacent facilities, etc.
(*71) The Rulebook on Contents of Information on Location and on Contents of Location
Permit.
(*72) Provisions of the Law on Planning and Construction, in this case, are not quite clear with respect to the formation of the building plot for construction of a biomass/biogas power plant. Article 69, paragraph 1, prescribes that, for construction of electric power facilities or equipment, a building plot of a smaller area may be formed than the area envisaged in the planning document for the particular zone, provided there is an access to the facility, or equipment, for the purpose of maintenance and elimination of defects or accidents.
(*73) Issuing of the water requirements, the water approval, and the water permit is regulated by the Law on Waters.
(*74) There is nothing prescribed as to what should be submitted with the application for the Opinion from RHMS – what has been specified herein is a general assessment of the author in line with the discussions in the specified organization.
(*75) There is nothing prescribed as to what should be submitted with the application for the Opinion from public water-management enterprises – what has been specified is a general assessment of the author in line with the discussions in the specified organizations.
(*76) The contents of the documentation, which shall be submitted with the application, are contained in the form VU, which can be downloaded from the Web site: www.minpolj.gov.rs / arhiva / vodoprivreda / vodoprivredna akta (Archive / Water Management / Water Documents). In compliance with the Law on General Administrative Procedure, the authority may request the Investor to complete the documentation.
(*77) Exceptionally, subject to Article 118, of the Law on Waters, the authority in charge of issuing the water requirements may request from the applicant to obtain the opinion of the Ministry of Environment and Spatial Planning and/or of a specialized scientific institution (establishments, institutes, etc.). For the facilities and works in a territory of a spa resort, the applicant shall obtain the opinion of the ministry in charge of the affairs of tourism. There is no specifically prescribed procedure for obtaining the above opinions.
(*78) To assist an applicant, the list of all the required documentation for obtaining the water documents can be found on the Web site of the Ministry of Agriculture, Forestry and Water Management: www.minpolj.gov.rs Link: Arhiva – Vodoprivreda - Vodna akta - Obrazac zahteva VS (Archive - Water Management – Water Documents - Application Form VS). Exhibits that shall be submitted can be downloaded from the Web site of the Ministry of Agriculture, Forestry and Water Management, Form VDP. In compliance with the Law on General Administrative Procedure, the authority may request the Investor to complete the documentation.
(*79) To assist an applicant, the list of all the necessary documentation for obtaining the water documents can be found on the Web site of the Ministry of Agriculture, Forestry and Water Management: www.minpolj.gov.rs Link: Arhiva – Vodoprivreda - Vodna akta - Obrazac zahteva VD (Archive – Water Management – Water Documents – Application Form VD). In compliance with the Law on General Administrative Procedure, the authority may request from the Investor to complete the documentation.
Note:
This text is taken from the document-guide for investors "Construction
of Plants and Electricity/Heat Generation from Biomass in the Republic
of Serbia", of which authors are Dr. Branislava Lepotic Kovacevic,
PhD Law, and Bojan Lazarevic, BSc El. Eng.The project was implemented under the patronage of USAID, GTZ / GIZ Serbia and the Ministry of Energy in 2010.