The station building in Prokop will be completed by October 20

Source: Politika Tuesday, 23.05.2023. 11:02
Comments
Podeli
(Photo: Urbanistički centar doo Beograd)
The construction of the Belgrade Center station building in Prokop will be completed by October 20, when its ceremonial opening is also planned, Ivan Vujicic, CEO of PFB, the main contractor, confirmed in an interview for Politika.

- Within the next two months, the installation of the steel structure and roofing will be completed, the installation of the facade structure and 85 percent of the facade glass will be completed, and the installation of the external solar and thermal protection system, will begin. The canopies will be completely done, and the other part to a lesser extent, in accordance with the dynamic plan. And the layers of flat roofs, insulation work, flat layers of the floor will be completely finished by then - says Vujicic and notes that the plan is to finish the ceramic works, the technical block of the building and traffic roads and parking lots in the next two months.

At the end of that period, the finishing works on the facade coverings, the internal aluminum-work and locksmith work will commence. The elevators and conveyors have arrived and the plan is to have about 70 percent of the installation work completed in the next two months. By the end of July, the arrangement of the ground floor on both sides of the building will be half finished, adds Vujicic.

The Belgrade Center station complex was initially designed as a single entity, but it is no longer so, since there was a user and ownership separation of the buildings at elevations 85 (underground, platform part) and 105 (the slab on which it is being built). In the future, Serbian Railways will manage only the station building, whereas the other 12 buildings will be five-story office buildings. Their investor is the Railway City company, the state's partner in this business.


(Photo: Urbanistički centar doo Beograd)

According to the project, the station building will have about 6,200 square meters and will include commercial space, offices, counter service, waiting room... Around this building, on the left and right sides, four additional buildings of five floors each will be constructed, and will be functionally separated. . Parking lots will be arranged on the edges of the slab on all sides, as well as a new garage on the part of the slab towards Senjak. The four buildings that are being built next to the station building will be completed in about a year and a half, and the other eight later.

The value of the construction of the station building, according to current estimates, is EUR 17 million.
Comments
Your comment
Full information is available only to commercial users-subscribers and it is necessary to log in.

Forgot your password? Click here HERE

For free test use, click HERE

Follow the news, tenders, grants, legal regulations and reports on our portal.
Registracija na eKapiji vam omogućava pristup potpunim informacijama i dnevnom biltenu
Naš dnevni ekonomski bilten će stizati na vašu mejl adresu krajem svakog radnog dana. Bilteni su personalizovani prema interesovanjima svakog korisnika zasebno, uz konsultacije sa našim ekspertima.