Construction of Solar Power Plant of 4.5 MW Planned in Novi Becej



The parcels are located in the East Business Zone in Novi Becej, and according to the data from the land register, there are no built facilities on them. The total area of the parcels is 63,675 m2.
The technical solution envisages the installation of 7,500 solar panels with a power of 600 W, which means that the peak power of the power plant would be 4.5 MW.
The dimensions of a solar panel are 2465 x 1134 x 35 mm, each weighing 31.1 kilograms. The panels are to be installed horizontally (“landscape”) on the supporting substructure at a 30-degree angle relative to the horizontal plane.
The peak monthly production is expected in July and amounts to 663.6 MWh. The lowest expected monthly production is projected for December, amounting to 110.7 MWh.
The owners of the land are Tatjana and Radislava Momirov, and the duration of the public presentation is seven days, beginning with April 27, 2023.

Naš izbor
Most Important News
13.11.2023. | Transport
State Becomes Owner of 100% of Shares of Air Serbia

13.11.2023. | Finance, IT, Telecommunications
Customs Administration Starts Applying eCustoms System

13.11.2023. | Finance, IT, Telecommunications
13.11.2023. | Industry, Construction, Transport
Machines for Production of Batteries and Fuel Cells to Be Assembled in Stara Pazova – Muehlbauer Automation to Build Technology Park Worth EUR 29.5 Million

13.11.2023. | Industry, Construction, Transport
01.12.2023. | News
What Burdens the Serbian-Montenegrin Cooperation and Where Are the Opportunities?

01.12.2023. | News
12.11.2023. | Construction, Transport
Krusevac to Be Connected to Highway in Early December?

12.11.2023. | Construction, Transport
30.11.2023. | Construction, Transport
Provincial Government Issues Permit for Construction of First Section of “Vojvodina Smile” Fast Route

30.11.2023. | Construction, Transport