Sunray Energy Planning Construction of Solar Power Plant of 990 kW in Arandjelovac



According to the urban project prepared by the Projektura studio from Belgrade, the estimated value of the investment is RSD 117,950,000 (around EUR 1 million).
The preliminary design for the construction of the photovoltaic power plant was prepared by Projektni biro i usluge AL&SA.
The following features need to be envisaged within the power plant:
– A field of solar panels set up on a metal structure elevated from the ground so that the land beneath the panel can be maintained and so that the maximum potential of solar energy for the concrete location can be used.
– Access routes, for accessing and maintaining the panels and the substation. These traffic routes are the corridors for the passing of the maintenance mechanization, with the finishing layer made of gravel, or earthen roads of the proscribed load-bearing capacity, depending on the characteristics of the terrain.
– A cable connection between the solar panels and the substations, as well as between the substations and the connection facility, for the input into the network of the electrical energy system of Serbia.
The land covered by this urban project is located in the southeast part of the administrative area of the municipality of Arandjelovac east of the IIB-grade state road no. 367, Arandjelovac-Donja Satornja, and is owned by the investor.

– The inverter – voltage transformer. This is a device that turns the direct voltage produced in solar panels into alternating voltage.
– The substation in which the electrical energy produced at the solar park is raised to the voltage level of 10 (20) kV, which can be let into the network according to the conditions of the company in charge of the distribution of electrical energy.
The photovoltaic panels are set up on the structure meant for the mounting of solar panels on the ground, at an angle of around 23 degrees relative to the horizontal plane and oriented toward the south. The total number of the photovoltaic panels is 2,184, with an individual installed power of 580 Wp. The total installed DC power in the photovoltaic panels is 1266.72 kWp, it is clarified in the urban project, which will be put up for public presentation until November 20.
S. T.
Naš izbor
Most Important News
13.11.2023. | Transport
State Becomes Owner of 100% of Shares of Air Serbia

13.11.2023. | Finance, IT, Telecommunications
Customs Administration Starts Applying eCustoms System

13.11.2023. | Finance, IT, Telecommunications
13.11.2023. | Industry, Construction, Transport
Machines for Production of Batteries and Fuel Cells to Be Assembled in Stara Pazova – Muehlbauer Automation to Build Technology Park Worth EUR 29.5 Million

13.11.2023. | Industry, Construction, Transport
07.12.2023. | Construction, Transport
Morava Corridor Section from Makresane to Kosevi Opens to Traffic

07.12.2023. | Construction, Transport
12.11.2023. | Construction, Transport
Krusevac to Be Connected to Highway in Early December?

12.11.2023. | Construction, Transport
07.12.2023. | Construction
Serbia to Get Modern Border Crossing with 6 Lanes Across HPP Djerdap 2 Dam – Tender Worth RSD 387 Million Published

07.12.2023. | Construction