New Flotation at Veliki Krivelj Mine to Increase Dry Ore Processing to 23.1 Million Tons – Zijin Files Request for Project’s Environmental Impact Assessment



As announced earlier, around 30% of the works on the construction of a new flotation at Veliki Krivelj were carried out by April 2021, and the value of the investment is USD 57.8 million.
According to the project, the new flotation at Veliki Krivelj is to be done with a capacity of 13.2 Mt, parallel and independent from the existing one, whose capacity is 9.9 Mt of dry ore.
The new flotation will be built close to the existing one, east of the flotation, beneath the existing copper filtering location. The total area of the industrial zone will amount to around 2,266 m2.
Naš izbor
Most Important News
13.11.2023. | Transport
State Becomes Owner of 100% of Shares of Air Serbia

13.11.2023. | Finance, IT, Telecommunications
Customs Administration Starts Applying eCustoms System

13.11.2023. | Finance, IT, Telecommunications
13.11.2023. | Industry, Construction, Transport
Machines for Production of Batteries and Fuel Cells to Be Assembled in Stara Pazova – Muehlbauer Automation to Build Technology Park Worth EUR 29.5 Million

13.11.2023. | Industry, Construction, Transport
01.12.2023. | News
What Burdens the Serbian-Montenegrin Cooperation and Where Are the Opportunities?

01.12.2023. | News
12.11.2023. | Construction, Transport
Krusevac to Be Connected to Highway in Early December?

12.11.2023. | Construction, Transport
30.11.2023. | Construction, Transport
Provincial Government Issues Permit for Construction of First Section of “Vojvodina Smile” Fast Route

30.11.2023. | Construction, Transport