Test operations of wind farm near Ulcinj – Commercial power production from this autumn

Source: Tanjug Thursday, 06.06.2019. 13:49
Comments
Podeli
IllustrationIllustration
The wind farm at Mozura in the municipality of Ulcinj has started its test operations, which will take 90 days, the Ministry of Economy of Montenegro announced.

– The technical acceptance procedure is in progress and should be completed within 90 days of the beginning of test operations, when the commercial power production is expected to start. The wind farm at Mozura will thereby get an exploitation permit – the ministry told Dnevne Novine, CdM reports.


After the test run of the power facility in Ulcinj, during which the wind farm will be checked for harmonization with the network, the Ministry of Sustainable Development and Tourism will issue the exploitation permit, which is a requirement for Mozura to be connected to the power system.
Comments
Your comment
Full information is available only to commercial users-subscribers and it is necessary to log in.

Forgot your password? Click here HERE

For free test use, click HERE

Follow the news, tenders, grants, legal regulations and reports on our portal.
Registracija na eKapiji vam omogućava pristup potpunim informacijama i dnevnom biltenu
Naš dnevni ekonomski bilten će stizati na vašu mejl adresu krajem svakog radnog dana. Bilteni su personalizovani prema interesovanjima svakog korisnika zasebno, uz konsultacije sa našim ekspertima.