Structural design of Montenegrin highway to Serbia late
So far, 80% of the design and 40% of the revised and approved main project have been completed.
This, however, doesn’t necessarily mean that the main works will be late, as the contractor has proposed corrective measures in order to honor the planned deadline, the report says.
It is added that the geological, field and geodetic surveys have been fully completed, whereas 90% of the study of the survey results has been completed. The layout and the height have also been fully defined, B92 reports.
The construction of the priority Smokovac-Uvac-Matesevo section of 41 km started on May 11, 2015, and the Chinese companies were given a deadline period of four years to complete the works.
Most Important News
06.04.2024. | Agriculture
Preconditions for Placement of Fresh Blueberries and Dried Plums in Chinese Market Secured
16.04.2024. | News
Jovan Ciric, Leasing Director Retail MPC Properties – MPC Echo symbolizes our desire for good ideas and innovative endeavors to spread freely and bring about positive changes
16.04.2024. | News
10.04.2024. | Finance, IT, Telecommunications, Tourism, Sports, Culture
Creative Industry – What This Serbian Economy Sector Worth EUR 2 Billion Encompasses
10.04.2024. | Finance, IT, Telecommunications, Tourism, Sports, Culture
18.04.2024. | Industry, Finance
Here come the new hunters for Serbian gold – Australian Strickland Metals buys mining project on mountain Rogozna
18.04.2024. | Industry, Finance
16.04.2024. | News
Economy Fair in Mostar opens – 26 companies from Serbia exhibiting
16.04.2024. | News
18.04.2024. | Transport
Jovanovic: Purchase of Siemens trams produced in Kragujevac for GSP Beograd should be considered
18.04.2024. | Transport